Blog Archives


STH roadway bridges

STH 145 Roadway & Bridges

KSingh was retained by WisDOT to perform construction inspection on this project along Fond Du Lac Avenue from County Line Road to 68th Street in Milwaukee County. This project included… Read the full article.

STH reconstuction

STH 59 Reconstruction

KSingh provided construction management services for an $8.5 million reconstruction of STH 59 in the City of Whitewater. This project was built in three stages over two years to improve… Read the full article.

STH reconstruction

STH 36 Reconstruction

KSingh performed construction inspection of the $9 million STH 36 (Milwaukee Avenue) Reconstruction project from STH 20 to CTH Y in Racine County. This project consisted of milling and paving… Read the full article.

STH reconstruction

STH 32 Reconstruction

KSingh was retained by the Wisconsin Department of Transportation to provide construction management services for the $6.1 million urban reconstruction along STH 32 in the City of Racine. The work… Read the full article.

layton avenue reconstruction

Layton Avenue Reconstruction

KSingh was retained by Milwaukee County to lead the construction management of a 1.1-mile corridor from S. 27th Street to W. Loomis Drive on Layton Avenue in Greenfield. The work… Read the full article.

Lake Butte de Morts Bridge

Lake Butte de Morts Bridge

The KSingh Team was retained to oversee the filling of Lake Butte des Morts and construction of Lake Butte des Morts Drive. Construction was completed ahead of schedule and with… Read the full article.

CTH F new alignment

CTH F New Alignment

KSingh provided construction management on a new alignment of CTH F in the City of Twin Lakes in Kenosha County. The purpose of the new alignment was to make it… Read the full article.

milwaukee street car

Milwaukee Streetcar The Hop MKE

KSingh was retained by the City of Milwaukee as part of a team to perform a Phase 1 Hazardous Material Assessment for the extension of the Streetcar from the existing… Read the full article.

milwaukee county airports

Milwaukee County Airports

KSingh has provided engineering design and construction management for several projects at the former General Mitchell International Airport including design services for the ground transportation restroom facility, the College Avenue… Read the full article.

bus rapid transit

Bus Rapid Transit

The Bus Rapid Transit project involved KSingh providing land surveying services to assist in the development of a 9-mile bus rapid transit system between downtown Milwaukee and Milwaukee Regional Medical… Read the full article.

Hart Woodman Road Bridge

Hart Road & Woodman Road Bridges

As part of the IH 39/90 South Segment team, KSingh was tasked with providing structural engineering for the replacements of the Woodman Road and Hart Road overpass bridges. The existing… Read the full article.

HWY H Bain Station

CTH H & Bain Station Road Roundabout

KSingh was retained to provide construction management services for the new roundabout at the intersection of CTH H and Bain Station Road in the Village of Pleasant Prairie in Kenosha… Read the full article.

USH split

USH 41/45 Split

KSingh was retained by WisDOT’s Southeast Region to perform three different construction management projects from the Washington County Line to the USH 41/45 split. This $24 million project required multiple… Read the full article.

CTH YY reconstuction

CTH YY Reconstruction

Scope of Services Preliminary and Final Design Drainage & Detention Right of Way Plat/Slopes Geotechnical Report Hazmat Investigation Phase I Wetland Delineation Environmental Documents Utility Coordination Public Involvement Signalized Intersection… Read the full article.

CTH D bridge replacement

CTH D Bridge Replacement

KSingh provided structural engineering for the replacement of the CTH D Bridge in the Village of Rochester. The bridge was closed during construction and there were several unique design challenges… Read the full article.

Sharon Road Bridge Replacement Janesville, WI

Sharon Road Bridge Replacement

KSingh was retained by the City of Janesville and WisDOT for the design of the replacement of the Sharon Road Bridge over Spring Brook Creek. The existing structure was a… Read the full article.

STH 50 / I 94 Interchange

STH 50 / I 94 Interchange

Scope of Services Concrete Pavement HMA Pavement Traffic Control Grading Storm Sewer Curb & Gutter Traffic Signals Street Lighting Pavement Marking

USH 41 Corridor

USH 41 Corridor

KSingh was retained by the Wisconsin Department of Transportation to perform construction management services for the reconstruction of the south segment of the US 41 conversion mega-project in Winnebago County…. Read the full article.

Lift Bridge

Lift Bridge Design & Construction

KSingh has been retained by the City of Milwaukee, WisDOT, and various consultants to provide construction management services for several lift bridges in the State of Wisconsin. The West Wisconsin… Read the full article.

Hoan Bridge Design

Hoan Bridge Design

Scope of Services Structural Engineering Bridge Deck Rehabilitation Hazardous Materials Assessment Survey